    We are to close on our loan on Friday, midday. Once those signatures hit paper, this is roughly what our schedule looks like:

    March/April: Design, starting with rough schematics running through final design

    late April/May: final design, construction documents, engineering, bidding

    May: permitting process begins with Salt Lake City

    mid-June: possibility of beginning construction on footings and foundation

    late June/early July: permits issued, construction begins in earnest

    July through late December: construction

    mid-January 2010: Construction loan comes due and we convert to permanent financing and move in...


    Oh my...what a year!