We are to close on our loan on Friday, midday. Once those signatures hit paper, this is roughly what our schedule looks like:
March/April: Design, starting with rough schematics running through final design
late April/May: final design, construction documents, engineering, bidding
May: permitting process begins with Salt Lake City
mid-June: possibility of beginning construction on footings and foundation
late June/early July: permits issued, construction begins in earnest
July through late December: construction
mid-January 2010: Construction loan comes due and we convert to permanent financing and move in...
Oh my...what a year!